PHOTOS: Ongoing construction on 2nd Niger bridge

PHOTOS: Ongoing construction on 2nd Niger bridge
November 20
20:38 2019

Julius Berger Nigeria Plc has released a progress report of the ongoing construction of the 2nd Niger Bridge.

In June, the company had launched a website to “allow Nigerians track the status” of the project.

The company said the project is expected to be completed by February 2022, adding that the scope of works include the construction of 1.6km long bridge, 10.3km highway, Owerri interchange and a toll station.

Below are the pictures:

Advertisement

Earthworks CH 33+200 – Working platform for GEC

Soil Improvement CH 32+100 LHS – Installation of PVD

Soil Improvement CH 31+750 – Laying of geotextile

Soil Improvement CH 30+175 – Installation of GECs

Single Box Culvert CH 29+800 – Formwork and reinforcement

Eastern Approach – Casting station – Installation of reinforcement for pile cap

Eastern Approach – Axis 330 – Installation of wall reinforcement

Niger Bridge Axis 260 – Pier table – Bottom part (North and South) completed

Western Approach Axis 240 – Pier head completed

Western Approach Axis 110 – 150 – Installation of lateral guide

Western approach –Casting station – Web and bottom reinforcement for Segment 1

Amakon bridge – Installation of precast I beams

Earthworks CH 25+000 to 25+100 – Hydraulic dredging into alignment

Download full progress report here

Click on the link below to join TheCable Channel on WhatsApp for your Breaking News, Business Analysis, Politics, Fact Check, Sports and Entertainment News!

Tags

0 Comments

No Comments Yet!

There are no comments at the moment, do you want to add one?

Write a comment

Write a Comment

error: Content is protected from copying.